6                                            WATER QUALITY Assessment

6.1                                      Introduction

This Section presents an evaluation of the potential water quality impacts from the construction and operation of the Project.  Mathematical modelling has been used to predict potential impacts to hydrodynamics, sediment transportation and water quality, the results of which have then been assessed with reference to the relevant environmental legislation, standards and tolerance criteria.

6.2                                      Relevant Legislation and Guidelines

The following legislation and relevant guidance or non-statutory guidelines are applicable to the evaluation of water quality impacts associated with the construction and operation of the Project.

·           Water Pollution Control Ordinance (WPCO);

·           Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM- ICW);

·           Environmental Impact Assessment Ordinance (Cap. 499. S.16) and the Technical Memorandum on EIA Process (EIAO-TM), Annexes 6 and 14; and

·           Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN1/94).

6.2.1                                Water Pollution Control Ordinance (WPCO)

The Water Pollution Control Ordinance (WPCO) is the primary legislation for the control of water pollution and water quality in Hong Kong.  Under the WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs).  Each WCZ has a designated set of statutory Water Quality Objectives (WQOs). The proposed Project is located within the Deep Bay WCZ.  The WQOs designated for this zone are thus relevant for assessing the water quality impacts from the construction and operation of the Project.

6.2.2                                Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM- ICW)

All discharges during both the construction and operation phases of the proposed development are required to comply with the Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-ICW) issued under Section 21 of the WPCO.

The TM-ICW defines acceptable discharge limits to different types of receiving waters.  Under the TM-ICW, effluents discharged into the drainage and sewerage systems, inshore and coastal waters of the WCZs are subject to pollutant concentration standards for specified discharge volumes.  These are defined by the Environmental Protection Department (EPD) and are specified in licence conditions for any new discharge within a WCZ.

6.2.3                                Technical Memorandum on EIA Process (EIAO-TM)

Annexes 6 and 14 of the EIAO-TM provide general guidelines and criteria to be used in assessing water quality impacts.

6.2.4                                Practice Note for Professional Persons, Construction Site Drainage

Apart from the above statutory requirements, the Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94), issued by EPD in 1994, also provide useful non-statutory guidelines on water pollution associated with construction activities.

6.3                                      Baseline Conditions

6.3.1                                Hydrology and Hydrodynamics

The mouth of Shenzhen River is located near the Pearl River estuary.  Shenzhen River originates from Wutong Mountain at an elevation of 214 m above sea level.  The river of total length 33 km is flowing west to Deep Bay. 

Shenzhen River is located within the subtropical region with distinct wet and dry seasons.  The average annual rainfall is around 1,900 mm.  The wet season from April to October contributes about 90% of the total annual rainfall.  Rainfall is the main supply of freshwater to Shenzhen River and the amount of run-off is closely related to rainfall.  Run-off during the wet season accounts for more than 87% of the total annual run-off. 

For the section of Shenzhen River within the Project Site, the average annual run-off volume from Qiannian Drainage is approximately 16,480,000 m3 and the average flow rate is about 0.522 m3 s-1, while the average annual run-off volume and flow rate from River Ganges (Ping Yuen River) are 32,550,000 m3 and 1.032 m3 s-1, respectively.  This section of the Shenzhen River comprises a “fan-shaped” system which is short and steep with faster flow rate.  Large flow from this section can converge into the downstream section within a short period of time. 

The river section downstream of the Ping Yuen River confluence is regarded as the downstream area of Shenzhen River.  In this area, the river course is winding on flat alluvial coastal plain.  After the Stage III regulation, the Ping Yuen River confluence and the mouth of Shenzhen River are almost at the same elevation.  According to the results of two hydrology surveys in 2004 and 2005, the maximum water level at high tide is decreasing downstream.  The difference in maximum water levels between Ng Tung River and Shenzhen River mouth is about 20 cm during high tide, while the difference during the low tide is small.  During periods of spring and neap tide, the flow rate of Shenzhen River increases downstream which reflects the increasing tidal influence downstream of the river. 

6.3.2                                River Water Quality

The proposed Project starts from Pak Fu Shan down to the confluence of Ping Yuen River (see Figure 6.1).  Within the HKSAR boundary, water courses identified within the Study area (defined as 500 m from the boundary of the Project Site) include the Shenzhen River, Kong Yiu Drainage Channel and Ping Yuen River (see Figure 6.1).  The Study area falls within the Deep Bay WCZ and the WQOs designated for the whole zone, inland waters and subzone Ganges are thus relevant to this Project and are summarized on Table 6.1.

Table 6.1       Key Water Quality Objectives of the Deep Bay WCZ for Shenzhen River, Kong Yiu Drainage Channel and Ping Yuen River

Water Course within the Study area

pH Range

Maximum 5-day Biochemical Oxygen Demand (BOD5)

Maximum Chemical Oxygen Demand (COD)

Maximum Annual Median Suspended Solids (SS)

Minimum Dissolved Oxygen

(DO)

Maximum Annual Mean Unionised Ammoniacal Nitrogen

Shenzhen River and Kong Yiu Drainage Channel

6.5 – 8.5

5 mg L-1

30 mg L-1

20 mg L-1

4 mg L-1

0.021 mg L-1

Ping Yuen River

6.5 – 8.5

3 mg L-1

15 mg L-1

20 mg L-1

4 mg L-1

0.021 mg L-1

Water Quality of the Shenzhen River

Routine river water quality monitoring along the Shenzhen River has been conducted by the Shenzhen Environmental Monitoring Centre.  Data of key water quality parameters measured during the period of 2007 to 2009 are extracted from six monitoring stations and presented in Tables 6.2 to 6.4.  These monitoring stations are located within as well as downstream of the Study area (see Figure 6.2).  Measurements were taken once per month from Jing Du and Quarry and twice per month from the other stations.

The monitoring data indicates that river water quality at the upstream area is better than that at the downstream area of the Shenzhen River (Tables 6.2 to 6.4).  The levels of nutrients, Chemical Oxygen Demand (COD), 5-day Biochemical Oxygen Demand (BOD5) and faecal coliforms are increasing from Jing Du to Ludang Village, after which the levels drop sharply which is probably as a result of tidal influence in the area when approaching the Shenzhen River mouth.  For dissolved oxygen (DO), the values were generally higher at the upstream area (ie Jing Du and Quarry) and dropped sharply after reaching the monitoring station at Lo Wu.  Generally, DO, COD and BOD5 show non-compliances with the WQOs at downstream stations including Lo Wu, Ludang Village, Pier and Shenzhen River mouth. 

Table 6.2        Annual Mean of Key Water Quality Parameters at the Shenzhen River Routine Water Quality Monitoring Stations in 2007

Station /

Parameter

River WQOs

Jing Du

Quarry

Lo Wu

Ludang Village

Pier

Shenzhen River Mouth

Water Temperature (ºC)

n.a.

22.8

25.1

24.9

25.0

25.0

25.0

pH

6.5 – 8.5

7.63

7.34

7.22

7.21

7.23

7.23

DO (mg L-1)

≥ 4

7.171

6.402

0.955

0.930

1.075

1.164

COD (mg L-1)

30

4.4

11.8

22.8

35.7

25.9

34.5

BOD5 (mg L-1)

5

1.01

3.21

5.38

12.26

9.05

13.15

Ammoniacal Nitrogen (mg L-1)

n.a.

0.30

8.47

14.05

21.13

18.42

19.39

Total Phosphorus (mg L-1)

n.a.

0.054

0.425

1.122

1.687

1.577

1.814

Total Nitrogen (mg L-1)

n.a.

1.06

11.15

16.07

24.02

20.03

22.36

Faecal Coliforms (104 cfu L-1)

n.a.

1

173

5,697

17,593

12,659

9,369

Notes:

(a)        Bold and underlined figures indicate non-compliance with the WQOs.

(b)        See Figure 6.2 for locations of the monitoring station.

(c)        n.a. indicates the absence of applicable WQOs.

Table 6.3        Annual Mean of Key Water Quality Parameters at the Shenzhen River Routine Water Quality Monitoring Stations in 2008

Station /

Parameter

River WQOs

Jing Du

Quarry

Lo Wu

Ludang Village

Pier

Shenzhen River Mouth

Water Temperature (ºC)

n.a.

22.5

24.1

24.0

24.2

24.2

24.3

pH

6.5 – 8.5

7.45

7.29

7.08

7.14

7.16

7.22

DO (mg L-1)

≥ 4

7.6

6.61

1.64

1.00

1.32

1.42

COD (mg L-1)

30

9.7

17.4

24.3

47.4

35.9

41.9

BOD5 (mg L-1)

5

1.1

3.8

8.1

17.2

14.4

16.7

Ammoniacal Nitrogen (mg L-1)

n.a.

0.11

6.44

12.47

19.00

16.68

15.64

Total Phosphorus (mg L-1)

n.a.

0.051

0.367

0.971

1.563

1.259

1.271

Total Nitrogen (mg L-1)

n.a.

1.10

12.45

15.18

21.93

18.94

17.73

Faecal Coliforms (104 cfu L-1)

n.a.

2

30

540

2800

1500

1300

Notes:

(a)     Bold and underlined figures indicate non-compliance with the WQOs.

(b)     See Figure 6.2 for locations of the monitoring station.

(c)     n.a. indicates the absence of applicable WQOs.

Table 6.4        Annual Mean of Key Water Quality Parameters at the Shenzhen River Routine Water Quality Monitoring Stations in 2009

Station /

Parameter

River WQOs

Jing Du

Quarry

Lo Wu

Ludang Village

Pier

Shenzhen River Mouth

Water Temperature (ºC)

n.a.

21.1

22.7

23.1

23.3

22.8

23.1

pH

6.5 – 8.5

7.64

7.33

7.03

7.10

7.08

7.08

DO (mg L-1)

≥ 4

6.933

5.373

0.728

0.457

0.480

0.616

COD (mg L-1)

30

4.6

12.9

45.2

74.2

55.1

59.5

BOD5 (mg L-1)

5

0.64

2.61

17.04

26.32

19.17

20.03

Ammoniacal Nitrogen (mg L-1)

n.a.

0.06

6.64

18.32

30.00

21.70

19.93

Total Phosphorus (mg L-1)

n.a.

0.013

0.435

1.224

2.216

1.587

1.569

Total Nitrogen (mg L-1)

n.a.

0.39

13.23

20.96

33.54

25.00

23.50

Faecal Coliforms (104 cfu L-1)

n.a.

1

39

2783

15842

2933

2311

Notes:

(a)     Bold and underlined figures indicate non-compliance with the WQOs.

(b)     See Figure 6.2 for locations of the monitoring station.

(c)     n.a. indicates the absence of applicable WQOs.

EPD has also undertaken routine river water quality monitoring in Hong Kong and one of the monitoring stations in North-western New Territories, GR1, is located at the downstream section of Ping Yuen River within the Study area (see Figure 6.2).  The monitoring data from GR1 in the period of 2006 to 2008 are extracted from the Annual River Water Quality Reports ([1]) ([2]) ([3]) and presented on Table 6.5.  The Water Quality Index at GR1 was graded as bad in 2006 and improved to fair in both 2007 and 2008.  In 2008, the WQO compliance rate at GR1 was only 47% ([4]). 

River Water Quality within the Study Area

As part of the EIA Study, a more focussed baseline water quality survey was carried out within the Study Area in the wet and dry seasons of 2009.  The locations of monitoring stations are illustrated in Figure 6.3 which cover the sections of Shenzhen River, Ping Yuen River and Kong Yiu Drainage Channel within the Study Area.  Results of the baseline survey are shown in Tables 6.6 and 6.7.  For the Shenzhen River, monitoring data from three stations indicate that the values of total nitrogen and total phosphorus are increasing downstream from S1 to S3, while faecal coliforms and ammoniacal nitrogen reached their peak values at S2.  Exceedances of the WQOs are observed for DO (see Table 6.6).  For the two tributaries, non-compliances with WQOs of COD and BOD5 are observed at the monitoring station of Ping Yuen River only in both wet and dry seasons.

6.3.3                                Discharges into the Shenzhen River

Direct discharge of domestic sewages from the households of Shenzhen is the main source of pollution to the river section of the Project Site.  Twenty-one sewage outlets from Shenzhen are identified as the source of major pollutants including BOD5, COD, ammoniacal nitrogen, total phosphorus and total nitrogen.  According to the Planning and Feasibility Study of the Project, the sewage discharge volume to the Shenzhen River is estimated to be 27,000 m3 per day ([5]).  The predicted discharge concentrations of BOD5, COD, ammoniacal nitrogen, total phosphorus and total nitrogen are 200, 300, 30, 4.5 and 35 mg L-1, while the daily discharge volume are 15.6, 23.4, 2.34, 0.35 and 2.73 tonnes, respectively.

A total of eight main discharge sources to the Shenzhen River are identified within and downstream of the Project Site, including Luofang Sewage Treatment Plant, Ping Yuen River, Shawan River, Ng Tung River, Buji River, Binhe Sewage Treatment Plant, Futian River and Huanggong River.  Water quality at these sources and the volume and quantities of pollutants from them have been monitored in 2009 as part of the EIA Study (see Figure 6.4) and presented in Tables 6.8 and 6.9, respectively.


 Table 6.5      Values of Key Water Quality Parameters at Station GR1 of Ping Yuen River from 2006 to 2008 (Data extracted from EPD Annual River Water Quality Reports)

Parameter

Unit

River WQOs

2006

2007

2008

Dissolved Oxygen

mg L-1

≥ 4

6.2

6.6

6.1

(1.7 – 8.0)

(3.4 – 11.1)

(3.0 – 8.4)

pH

 

6.5 – 8.5

7.6

7.4

7.2

(6.8 – 8.1)

(7.2 – 8.0)

(6.6 – 7.4)

Suspended solids

mg L-1

20

50

14

22

(23 – 660)

(1 – 110)

(13 – 450)

BOD5

mg L-1

3

38

7

8

(4 – 170)

(3 – 160)

(2 – 52)

COD

mg L-1

15

60

26

25

(7 – 1,100)

(9 – 220)

(8 – 250)

Oil and Grease

mg L-1

n.a.

1.0

0.5

0.6

(0.5 – 26.0)

(0.5 – 12.0)

(<0.5 – 5.3)

Faecal coliforms

cfu/100ml

n.a.

320,000

160,000

160,000

(60,000 – 1,700,000)

(32,000 – 1,200,000)

(16,000 – 35,000,000)

E. coli

cfu/100ml

n.a.

230,000

67,000

35,000

(34,000 – 1,700,000)

(14,000 – 770,000)

(5,000 – 800,000)

Ammonia -Nitrogen

mg L-1

n.a.

36.00

4.70

6.05

(3.10 – 210.00)

(1.20 – 45.00)

(0.41 – 24.00)

Nitrate-nitrogen

mg L-1

n.a.

0.28

0.80

0.61

(0.01 – 1.30)

(0.01 – 1.90)

(<0.01 – 1.20)

Total Kjeldahl nitrogen

mg L-1

n.a.

44.00

6.20

7.70

(3.50 – 300.00)

(2.30 – 59.00)

(0.81 – 28.00)

Ortho-phosphate

mg L-1

n.a.

7.15

1.4

1.8

(0.77 – 28.00)

(0.19 – 8.90)

(0.22 – 6.60)

Total phosphorus

mg L-1

n.a.

8.60

1.8

2.25

(0.98 – 51.00)

(0.52 – 11.00)

(0.39 – 11.00)

Total sulphide

mg L-1

n.a.

0.06

0.02

0.02

(0.02 – 0.22)

(0.02 – 0.31)

(<0.02 – 2.00)

Aluminium

μg L-1

n.a.

155

115

120

(70 – 900)

(50 – 380)

(<50 – 380)

Cadmium

μg L-1

n.a.

0.1

0.1

<0.1

(0.1 – 0.2)

(0.1 – 0.2)

(<0.1 – <0.1)

Chromium

μg L-1

n.a.

1

1

<1

(1 – 6)

(1 – 1)

(<1 – 2)

Copper

μg L-1

n.a.

13

5

4

(4 – 23)

(3 – 41)

(2 – 9)

Lead

μg L-1

n.a.

2

2

3

(1 – 6)

(1 – 6)

(<1 – 10)

Zinc

μg L-1

n.a.

40

40

25

(20 – 350)

(10 – 1,600)

(10 – 170)

Notes:

(a)        Data presented are in annual medians of monthly samples; except those for faecal coliforms and E. coli which are in annual geometric means;

(b)        Figures in brackets are annual ranges.

(c)        NM indicates no measurement taken.

(d)        Values at or below laboratory reporting limits are presented as laboratory reporting limits.

(e)        Equal values for annual medians (or geometric means) and ranges indicate that all data are the same as or below laboratory reporting limits.

(f)          Bold and underlined figures indicate non-compliance with the WQOs.

(g)        n.a. indicates the absence of applicable WQOs.


Table 6.6    Results of Baseline Water Quality Monitoring Conducted in the Wet and Dry Seasons, 2009, for Sections of Shenzhen River within the Study Area

Parameters

WQOs

Jing Du (S1)

Near the Mouth of Qiannian Drainage (S2)

Quarry (S3)

 

 

Wet Season

Dry Season

Annual Mean

Wet Season

Dry Season

Annual Mean

Wet Season

Dry Season

Annual Mean

Water Temperature ()

n.a.

27.85

21.5

24.68

29.5

20.6

25.05

29.7

23.6

26.65

DO (mgL-1)

≥ 4

7.86

7.00

7.43

4.30

3.64

3.97

5.55

6.4

5.98

pH

6.5 – 8.5

7.57

8

7.79

7.3

7.39

7.35

7.29

7.3

7.3

COD (mgL-1)

30

6.58

10.3

8.44

13.1

6.73

9.92

13.4

13.2

13.3

Permanganate index (mgL-1)

n.a.

0.93

2

1.47

3.3

2.12

2.71

3.75

4.8

4.27

BOD5 (mgL-1)

5

0.84

1.5

1.17

3.2

0.6

1.9

3.36

4.4

3.88

Ammoniacal Nitrogen (mgL-1)

n.a.

0.047

0.02

0.034

5

4.93

4.965

2.813

2.2

2.507

Total Nitrogen (mgL-1)

n.a.

0.148

0.3

0.224

5.7

8.27

6.985

7.836

10.7

9.268

Total Phosphorus (mgL-1)

n.a.

0.057

0.035

0.046

0.2

0.34

0.27

0.259

0.4

0.33

Fluoride (mgL-1)

n.a.

0.085

0.09

0.088

0.3

0.21

0.255

0.71

0.6

0.655

Hexavalent chromium (mgL-1)

n.a.

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

Mercury (mgL-1)

n.a.

0.04

0.04

0.04

0.04

0.04

0.04

0.04

0.04

0.04

Cyanide (mgL-1)

n.a.

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

Phenol (mgL-1)

n.a.

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

0.002

Anionic Surfactants (mgL-1)

n.a.

0.024

0.024

0.024

0.0337

0.146

0.08985

0.052

0.1

0.076

Sulphide (mgL-1)

n.a.

0.02

0.02

0.02

0.02

0.02

0.02

0.02

0.02

0.02

Copper (mgL-1)

n.a.

0.013

0.006

0.01

0.006

0.006

0.006

0.05

0.006

0.028

Zinc (mgL-1)

n.a.

0.007

0.04

0.024

0.007

0.005

0.006

0.022

0.014

0.018

Total Lead (mgL-1)

n.a.

0.8

0.0002

0.4001

0.8

0.0004

0.4002

0.8

0.0002

0.4001

Total Cadmium (mgL-1)

n.a.

0.1

0.00008

0.05004

0.07

0.00008

0.03504

0.148

0.00008

0.074

Selenium (mgL-1)

n.a.

0.44

0.0004

0.2202

0.47

0.004

0.237

0.625

0.004

0.3145

Total Arsenic (mgL-1)

n.a.

1.65

0.007

0.8285

1.27

0.003

0.6365

0.863

0.0031

0.433

Oil and Grease (mgL-1)

n.a.

0.02

0.02

0.02

0.03

0.02

0.025

0.02

0.02

0.02

Faecal coliforms (104/L)

n.a.

3.2

20.0

11.6

300.0

71.6

185.8

25.7

13.3

19.5

Notes:

(a)           Bold and underlined figures indicate non-compliance with the WQOs.

(b)           See Figure 6.3 for locations of the monitoring station.

(c)           n.a. indicates the absence of applicable WQOs.


Table 6.7        Results of Baseline Water Quality Monitoring Conducted in the Wet and Dry Seasons, 2009, for the Kong Yiu Drainage Channel and Ping Yuen River

Parameter

Kong Yiu Drainage Channel (S4)

Ping Yuen River (S5)

 

Season

River WQOs

Wet Season

Dry Season

River WQOs

Wet Season

Dry Season

Water Temperature ()

n.a.

 n.a.

20

n.a.

 n.a.

21

pH

6.5 – 8.5

7.2

7.3

6.5 – 8.5

7.5

7.2

Permanganate index (mgL-1)

n.a.

3.1

 n.a.

n.a.

5.17

 n.a.

COD (mgL-1)

30

8.7

19.3

15

30.5

21.1

BOD5 (mgL-1)

5

2.60

3.72

3

4.30

3.62

Ammoniacal Nitrogen (mgL-1)

n.a.

0.33

0.13

n.a.

3.09

13

Total Phosphorus

(mgL-1)

n.a.

0.28

0.12

n.a.

0.27

2.57

Total Nitrogen (mgL-1)

n.a.

1.33

2.47

n.a.

4.94

22.8

Copper (mgL-1)

n.a.

<0.006

<0.006

n.a.

<0.006

0.01

Zinc (mgL-1)

n.a.

0.01

 n.a.

n.a.

0.01

 n.a.

Notes:

(a)        Data presented are season mean.

(b)        n.a. indicates that no measurement was being taken.

(c)        Bold and underlined figures indicate non-compliance with WQOs.

(d)        n.a. indicates the absence of applicable WQOs.


Table 6.8        Water Quality Data Measured at the Sources of Discharge

Sources of Discharge

Season

Water Temperature ()

pH

Permanganate index (mgL-1)

COD (mgL-1)

BOD5 (mgL-1)

Ammoniacal Nitrogen (mgL-1)

Total Phosphorus (mgL-1)

Total Nitrogen (mgL-1)

Copper (mgL-1)

Zinc

(mgL-1)

Kong Yiu Drainage Channel

Wet

 

7.2

3.1

8.7

2.6

0.33

0.28

1.33

<0.006

0.01

Dry

20

7.3

 

19.3

3.72

0.13

0.12

2.47

<0.006

 

Ping Yuen River

Wet

 

7.5

5.17

30.5

4.3

3.09

0.27

4.94

<0.006

0.01

Dry

21

7.2

 

21.1

3.62

13

2.57

22.8

0.01

 

Shawan River

Wet

31

7.3

3.64

8.8

3.5

0.75

0.15

9.6

<0.006

0.01

Dry

 

7.5

 

29.9

6.2

4.54

0.54

16.3

<0.006

 

Ng Tung River

Wet

30

7.2

3.42

9.4

2.36

1.85

0.26

3.72

0.007

0.01

Dry

 

7.1

 

19.3

9.35

6.9

0.49

13.7

<0.006

 

Buji River

Wet

31

7.4

17.9

90.1

45.6

32.4

0.94

35.3

<0.006

0.03

Dry

 

7.2

 

102

56.7

36.9

1.06

47.3

0.006

 

Futian River

Wet

31

7.2

17.7

112

57.4

16.6

1.46

19.7

<0.006

0.01

Dry

 

7.2

 

61.1

28.7

18.5

1.95

35

<0.006

 

Huanggong River

Wet

31

7.3

11.8

61

30.8

15.8

0.91

17.3

<0.006

0.01

Dry

 

7.1

 

43.8

27.6

18.6

0.6

22.3

<0.006

 


Table 6.9       Quantities of Pollutants and Discharge Volume from the Sources of Discharge

Source of Discharge

Discharge Volumem3 d-1

Quantities of Pollutantskg d-1

 

 

Total Suspended Solids

COD

BOD5

Ammoniacal Nitrogen

Total Nitrogen

Total Phosphorus

Oil and Grease

Copper

Luofang Sewage Treatment Plant

350,000

3,850.00

7,700.00

350.00

108.50

1.19

126.35

28.00

0.21

Ping Yuen River

19,094

305.51

582.38

82.11

59.00

9.43

5.10

3.82

0.01

Shawan River

35,942

1,653.35

316.29

125.80

26.96

345.05

5.43

7.19

0.02

Ng Tung River

372,902

7,458.05

3,505.28

880.05

689.87

1,387.20

96.95

74.58

0.22

Buji River

48,7296

68,221.40

43,905.37

22,230.44

15,798.10

17,221

456.60

97.46

0.29

Binhe Sewage Treatment Plant

218,400

114.57

8,736.00

1,310.4

1,917.60

1.010

107.90

34.94

0.13

Futian River

777

44.32

87.17

44.63

12.89

15.33

1.13

0.16

0.00

Huanggong River

31,104

777.60

1,897.34

956.76

491.44

539.34

28.18

6.22

0.02


6.3.4                               Sediment Quality

The construction of the Project will require excavation and disposal of river sediments.  Under the Planning and Feasibility Study for Training of Upstream Section of Shenzhen River, twenty (20) river sediment samples were collected at five (5) locations within the Study Area and tested in accordance with the requirements stipulated in the ETWB TC(W) No. 34/2002 for an initial assessment of the nature of contaminated materials in the river sediment and the locations of the contaminated sediments (see Figure 6.5).  In addition, a sediment sampling programme has been undertaken as part of this EIA Study to delineate the locations of the contaminated sediment and enable subsequent estimation of different types of sediments (ie contaminated and uncontaminated sediments) to be disposed of for the purpose of the EIA. River bed sediment samples have been collected at eight (8) locations (see Figure 6.5). 

Detailed methodology and sediment quality results for the two sediment sampling programmes are presented in the Land Contamination and Waste Management Assessment Report while brief descriptions of the data are provided in Table 6.10.  The sediment quality data is compared against the sediment quality criteria specified in ETWB TC(W) No. 34/2002.  Sediment from 21 of the 33 samples tested are found to be uncontaminated (ie sediment with all contaminant levels not exceeding the LCEL) and classified as Category L materials (see Table 6.10).  The heavy metals concentrations in 6 samples were found between the LCEL and UCEL and thus classified as Category M contaminated materials.  The concentrations in 6 samples were found exceeded the UCEL and thus classified as Category H contaminated materials. 


Table 6.10     Summary of Sediment Sampling Results

Sampling Location (h)

Sampling Depth (m below river bed)

Metals and Metalloids (mg kg-1)

Low M.Wt PAHs (µg kg-1) (f)

High M.Wt PAHs (µg kg-1) (f)

Total PCBs (µg kg-1) (f)

TBT in interstitial water (µg L-1) (e) (f) (g)

Overall Sediment Class(a),(b),(c)

 

As

 Cd

Cr

Cu

Pb

Hg

Ni

Ag

Zn

Reporting Limits

 

1

0.2

1

1

1

0.05

1

0.1

1

< 550

< 1,700

< 3

0.015

 

LCEL(d)

 

12

1.5

80

65

75

0.5

40

1

200

550

1,700

23

0.15

 

UCEL(d)

 

42

4

160

110

110

1

40

2

270

3,160

9,600

180

0.15

 

SD1

Surface

2.8

0.42

10

<1.0

46

<0.05

5.9

0.18

52

ND

ND

ND

ND

L

SD1

0.9

3.5

0.21

<8.0

9.0

26

<0.05

<4.0

<0.10

20

ND

ND

ND

ND

L

SD1

1.9

<1.0

<0.20

<8.0

<1.0

16

<0.05

<4.0

<0.10

<20

ND

ND

ND

ND

L

SD1

2.9

<1.0

<0.20

<8.0

<1.0

12

<0.05

<4.0

<0.10

<20

ND

ND

ND

ND

L

SD2

Surface

1.1

1.3

52

82

120

0.21

24

1.3

430

ND

ND

ND

ND

H

SD2

0.9

3.1

0.25

<8.0

12

52

<0.05

<4.0

0.23

40

ND

ND

ND

ND

L

SD2

1.9

1.2

<0.20

<8.0

<1.0

22

<0.05

<4.0

<0.10

<20

ND

ND

ND

ND

L

SD2

2.9

12

0.48

<8.0

9.0

<8.0

<0.05

5.9

0.12

91

ND

ND

ND

ND

L

SD2

5.9

6.5

0.35

<8.0

8.7

19

<0.05

<4.0

<0.10

44

ND

ND

ND

ND

L

SD3

Surface

2.0

0.25

<8.0

9.9

37

<0.05

4.3

0.10

45

ND

ND

ND

ND

L

SD3

0.9

2.4

<0.20

<8.0

8.6

31

<0.05

<4.0

<0.10

22

ND

ND

ND

ND

L

SD3

1.9

8.5

1.7

26

14

50

<0.05

<4.0

<0.10

93

ND

ND

ND

ND

M

SD3

2.9

<1.0

0.27

9.6

14

<8.0

<0.05

7.3

<0.10

21

ND

ND

ND

ND

L

SD4

Surface

2.0

<0.20

<8.0

<1.0

34

<0.05

<4.0

<0.10

28

ND

ND

ND

ND

L

SD4

0.9

6.0

0.31

<8.0

11

50

<0.05

4.0

<0.10

48

ND

ND

ND

ND

L

SD4

1.9

11

1.6

12

40

170

<0.05

15

0.34

180

ND

ND

ND

ND

H

SD4

2.9

2.5

0.26

<8.0

42

62

<0.05

4.4

0.14

56

ND

ND

ND

ND

L

SD5

Surface

45

1.9

71

130

120

1.4

84

1.4

560

ND

ND

ND

ND

H

SD5

0.9

12

0.71

<8.0

30

160

<0.05

11

0.20

72

ND

ND

ND

ND

H

SD5

1.9

5.1

0.35

<8.0

14

120

<0.05

<4.0

<0.10

48

ND

ND

ND

ND

H

SD5

2.9

5.3

0.42

<8.0

14

100

<0.05

<4.0

0.10

61

ND

ND

ND

ND

M

SR1

Surface

2

<0.2

4

6

37

<0.05

3

<0.1

31

ND

ND

ND

NA

L

SR2

Surface

3

0.2

6

9

57

<0.05

3

0.2

44

ND

ND

ND

NA

L

SR3

Surface

6

0.4

28

31

78

<0.05

17

0.3

122

ND

ND

ND

NA

M

SR4

Surface

6

0.4

11

21

86

<0.05

13

0.1

71

ND

ND

ND

NA

M

SR4

0.9

3

0.2

9

21

54

<0.05

5

<0.1

45

ND

ND

ND

NA

L

SR4

1.9

5

0.2

7

12

58

<0.05

4

<0.1

34

ND

ND

ND

NA

L

SR4

2.9

1

<0.2

3

7

41

<0.05

2

<0.1

20

ND

ND

ND

NA

L

SR5

Surface

3

0.4

22

20

39

0.11

14

0.7

84

ND

ND

ND

NA

L

SR5

Dup

3

0.2

28

23

26

<0.05

16

0.2

92

ND

ND

ND

NA

L

SR6

Surface

7

0.8

8

14

97

<0.05

10

0.3

112

ND

ND

ND

NA

M

SR7

Surface

28

2.6

46

108

167

1.16

222

2.7

651

ND

ND

ND

NA

H

SR8

Surface

7

2.1

3

10

67

<0.05

4

0.1

228

ND

ND

ND

NA

M

Notes:

(a)  Category L = Sediment with all contaminant levels not exceeding the LCEL. 

(b)  Category M = Sediment with any one or more contaminant levels exceeding the LCEL and none exceeding the UCEL. 

(c)  Category H = Sediment with any one or more contaminant levels exceeding the UCEL. 

(d)  CEL = Chemical Exceedance Levels as stipulated in ETWB (TC) No. 34/2002.  These included the Lower and Upper Chemical Exceedance Levels (LCEL, UCEL).

(e)  NA = Not Available

(f)    ND = Not Detected

(g)  Analysis of tributyltin (TBT) in interstitial water was cancelled for samples collected during the EIA Study due to insufficient volume of interstitial water.

(h)  Locations with ID “SR” are sampled as part of the EIA Study while locations with ID “SD” are sampled as part of the FS Study.

(i)    Underlined figures indicate exceedance of the LCEL.

(j)    Bold and underlined figures indicate exceedance of the UCEL.


6.4                                      Water Quality Sensitive Receivers

The Water Quality Sensitive Receivers (WSRs) that may be affected by changes in water quality arising from the Project are identified in accordance with the EIAO-TM, which include the following:

·         Shenzhen River;

·         Kong Yiu Drainage Channel;

·         Ping Yuen River;

·         Wetland Conservation Area at Shenzhen River estuary; and

·         Mai Po and Inner Deep Bay Ramsar Site.

Locations of the above WSRs are shown in Figure 6.6 while the approximate shortest distance from the identified WSRs to the Project Site are detailed in Table 6.11.  Water from Shenzhen River will not intrude into any active fish pond and therefore, no active fish pond is identified as WSR within the Study Area.

Table 6.11      Identified Water Quality Sensitive Receivers (WSRs)

WSRs

Minimum Distance away from the Project Site Boundary (m)

Shenzhen River

Located within and next to the Project Site

Ping Yuen River

Located next to the Project Site

Kong Yiu Drainage Channel

Located next to the Project Site

Wetland Conservation Area at Shenzhen River estuary

7.8 km

Mai Po and Inner Deep Bay Ramsar Site

11 km

6.5                                      Potential Sources of Impact

Potential sources of impacts to water quality arising from the Project may occur during both the construction and operation phases.  Each is discussed below.

6.5.1                                Construction Phase

The main construction activities associated with the Project that have the potential to cause water quality impacts involve the following:

·           Cofferdam demolition (ie involves wet excavation by backhoes along the central line of the designed river course) after river widening, formation of flood detention pond and embankment;

·           Drainage from foundation pit for construction of new embankment;

·           Construction of boundary fence and boundary patrol road; and

·           Site runoff and pollutants entering the receiving waters.

River water will be diverted from the works area before the commencement of excavation and construction activities by constructing a cofferdam which will be made of hessian bags with clay.  Impact to water quality due to the river diversion is thus not expected to occur.  As the excavation of river bed will be carried out in dry condition within the cofferdam, release of suspended sediment, and hence water quality impact is not expected.

6.5.2                                Operation Phase

The potential impacts to water quality arising from operation of the Project have been identified as follows:

·           Changes to the hydrodynamics through the river regulation and thereby affecting the local erosion and sedimentation pattern and water quality; and

·           Maintenance dredging which may lead to disturbance and re-suspension of river sediments and thereby affecting water quality.

6.6                                      Assessment Methodology

6.6.1                                General Methodology

The methodology employed to assess the above impacts is presented in the Water Quality Modelling Method Statement (see Annex C1) and has been based on the information presented in the Project Description. 

Impacts to the concentrations of SS caused by the demolition of cofferdam and foundation pit drainage have been assessed using mathematic modelling.  It is planned to carry out river bed excavation during dry season.  However, the impact assessment has also taken into account excavation during both dry and wet seasons just in case if excavation during wet season is necessary.  The release of heavy metals, nutrients and micro-organic pollutants from the disturbed sediments caused by cofferdam demolition was also assessed.  Mitigation measures, as proposed in Section 6.9, were assumed to be absent in the modelling so that worse case scenarios were examined.

Operational impacts on water quality have also been studied by means of mathematical modelling.  The models have been used to simulate the effects of operation due to river regulation, including potential effects on flows and water levels and subsequent water quality effects due to changing hydrodynamics and dry weather flow interception works on the Shenzhen side, and any changes in local erosion and sedimentation. 

Full details of the working conditions examined in the modelling works are provided in Annex C1.  Figures presenting the modelling results are presented in Annex C2.  As Kong Yiu Drainage Channel and Ping Yuen River will not be affected by tidal influence, water from Shenzhen River will not intrude into these watercourses.  Hence, the water quality impact to Kong Yiu Drainage Channel and Ping Yuen River will only be assessed qualitatively, if found necessary.

6.6.2                                Uncertainties in Assessment Methodology

In order to study the worst case environmental impacts during construction and operation of the Project, it is conservatively assumed that all sediment released will be discharged into the receiving water.  The total sediment leaked would be treated as intensively discharging into the water body at the same time.  In reality, this would not happen and thus will represent a worst case scenario and it is a conservative assessment.

6.7                                      Impact Assessment

6.7.1                                Construction Phase

Suspended Sediment Dispersion

The main potential impacts to water quality arising from this Project during the construction phase relate to the re-suspension of river sediment caused by foundation pit drainage and cofferdam demolition.  The construction of cofferdam does not involve any excavation works and hence, will not lead to significant disturbance of the river sediments.  Unacceptable water quality impacts are thus not anticipated.  Drainage from the foundation pit will also lead to dispersion of suspended sediment from the works area.  The resulting suspended sediment dispersion will subsequently cause potential physico-chemical changes in the river water. 

It is noted that the demolition of cofferdam will involve the use of backhoes (1 m3) and long boom backhoes (0.55 m3) at different locations of the Project Site.  To assess the impacts of the demolition of cofferdam and drainage of foundation pits to the SS concentrations, a total of two working conditions have been modelled which assumed that the works are carried out concurrently among Work Areas I (near Changling Village) and II (near the proposed Liantang/Heung Yuen Wai Boundary Control Point (LT/HYW BCP)) and among Work Areas III (near Luofang Village) and IV (near Ping Yuen River confluence), respectively, for both wet and dry seasons (see Figure 6.1).  For each working condition, the sediment release rate of the backhoes was made reference to an open grab.  For comparison purpose, the use of closed grab was also modelled (see Annex C1).  As a conservative approach, the estimated total excavation volume of 100,000 m3 of the Project is assumed to be generated from wet excavation works only for calculation of the sediment release rate.  In the water quality model, the daily excavation rate adopted for each Work Area is 996 m3 day-1 for the dry season and 432 m3 day-1 for the wet season, respectively.

Foundation pits will be excavated within the cofferdam for the construction of the new dykes on both sides of the Shenzhen River.  Before the foundation pits are being filled, it is required to discharge wastewater from the pits regularly.  The foundation pit drainage, which contains certain amount of river sediment, will have the potential to increase the SS concentration of the river water in the vicinity of the works area during the construction phase.  According to the Guangdong Province Discharge Limits for Water Quality Pollutants (DB44/26-201), SS concentration in the foundation pit drainage shall not be higher than 100 mg L-1.  Adequate time (48 hours) will be allowed for the settlement of the suspended sediments to ensure that the aforementioned standard is met before foundation pit drainage are being discharged outside the works area.  The recommended flow rate of the foundation pit drainage is 0.17 m3 S-1.  With the adoption of the maximum allowable value of 100 mg L-1, the SS release rate from the foundation pit drainage is 0.017 kg s-1 and is adopted in the water quality model to predict the SS elevations caused by foundation pit drainage from the works area (see Annex C1).  It should be noted that foundation pit drainage and cofferdam demolition are not concurrent activities since the foundation pit will be filled for formation of embankment before demolition of cofferdam.  Therefore, they are not assessed as concurrent activities in the model.

The results from each working condition have been presented as average monthly SS concentration along the length of the modelled river section, presented as the distance from the most upstream point of the Stage IV Project Site (see Figures C-1 to C-4 of Annex C2).  According to the WQO for inland waters of the Deep Bay WCZ (including Ganges Subzone, Indus Subzone and other inland waters with the Study area), effluent discharge from the Project Site shall not cause the annual median of SS to exceed 20 mg L-1.  However, results of the water quality modelling show that baseline SS concentration within the Study area is well above 20 mgL-1 which limits the practicality to adopt such standard (see Figures C-1 to C-4 of Annex C2).  As effluent from the Project Site will eventually flow into Deep Bay through the Shenzhen River, the WQO for marine waters which states that effluent discharge shall not cause a 30% increase in SS level in the natural environment is used for the assessment.  This criterion is adopted to determine whether the increase of SS concentration in river water at 500 m upstream and 1,000 m downstream of the work area would cause unacceptable water quality impact (ie SS concentrations caused by construction activity > 130% of baseline SS concentrations).  It should be noted that the same criterion was adopted in the approved EIA study of the Shenzhen River Regulation Project Stage III ([6]).  Mitigation measures to reduce impacts to acceptable levels, if deemed necessary, are then recommended.

In summary, the following working conditions were set to assess the potential water quality impacts of cofferdam demolition and foundation pit drainage during the construction phase:

·           Condition 1: The SS concentrations with cofferdam demolition and foundation pit drainage near Changling Village (Work Area I) and the proposed LT/HYW BCP (Work Area II).

·           Condition 2: The SS concentrations with cofferdam demolition and foundation pit drainage near Luofang Village (Work Area III) and Ping Yuen River confluence (Work Area IV).

For both the dry and wet season periods, modelling results show that SS concentrations associated with foundation pit drainage and demolition of cofferdams using either open grab or closed grab are compliant with the assessment criterion (ie SS concentrations caused by construction activity at 500 m upstream and 1,000 m downstream of the work area < 130% of baseline SS concentrations) under the two working conditions (see Table 6.12; and Figures C-1 to C-4 of Annex C2).  According to the modelling results, foundation pit drainage and cofferdam demolitions will only lead to localised SS elevations downstream of the Work Areas and will not exert any impact at the upstream areas (see Figures C-1 to C-4 of Annex C2).  SS elevations associated with foundation pit drainage show compliance with the assessment criterion along the entire river section.  For Work Area I and Work Area II (ie Working Condition 1), SS concentrations exceeding 130% of the baseline concentrations are anticipated in a region of 900 m and 790 m downstream of the cofferdam demolition activity near the proposed LT/HYW BCP for the dry and wet season, respectively.  For Work Area III and Work Area IV (ie Working Condition 2), SS concentrations exceeding 130% of the baseline conditions are predicted by the water quality model within a region of 660 m downstream of the cofferdam demolition activity near the Ping Yuen River confluence in both seasons.  No WSRs are located within the regions mentioned above.  Unacceptable water quality impacts are thus not expected to occur and mitigation measures are considered not necessary.

It is therefore anticipated that no adverse water quality impacts would arise from cofferdam demolition and foundation pit drainage.

The elevated SS caused by the construction activities is localised to the vicinity of the Project Site (see Figures C-1 to C-4 of Annex C2).  Concentrations of SS at the mouth of Shenzhen River during the construction activities are the same as the baseline concentrations under all working conditions (see Table 6.12).  Therefore, it is anticipated unacceptable impacts to the Wetland Conservation Area and Mai Po and Inner Deep Bay Ramsar Site near the Shenzhen River mouth will not occur. 

Overall, no adverse impacts to SS concentrations are anticipated to occur as a result of the cofferdam construction and demolition and foundation pit drainage.

Heavy Metals, Nutrients and Micro-Organic Pollutants

Elutriate tests (sediment to water ratio of 1:4) were carried out to assess the potential for the release of heavy metals (including arsenic, cadmium, chromium, copper, lead, nickel, silver and zinc), nutrients (including ammoniacal nitrogen, total nitrogen and total phosphorus) and micro-organic pollutants (including PAHs, PCBs and chlorinated pesticides) from the river sediments as they are disturbed/agitated through wet excavation during cofferdam demolition.  Sediment samples collected under the EIA Study from five out of eight sediment sampling locations (see Figure 6.5) were tested and results are shown in Table 6.13 (please refer to Annex C3 for the detailed laboratory analysis results).  Results of the elutriate tests show that levels of all heavy metals and micro-organic pollutants are below the reporting limits and within the assessment criteria (Table 6.14).  Levels of total nitrogen, ammoniacal nitrogen and total phosphorus were recorded above the reporting limits, consequently, the water quality impacts associated with the release of these nutrients from the disturbed river sediments are further evaluated. 

Compared with the water quality data of the Shenzhen River collected by the Shenzhen Environmental Monitoring Centre (Tables 6.2 to 6.4), it is found that the concentrations of total nitrogen, total phosphorus and ammoniacal nitrogen from the elutriate tests (Table 6.14) are generally similar to the concentrations recorded by the Centre at stations downstream of the Project Site from 2007 to 2009.  It is thus anticipated that nutrients release from the disturbed sediments as a result of the excavation works within the Project Site will not lead to unacceptable water quality impacts to the downstream area.  In addition, the modelling results show that during construction, SS concentrations at the WSRs (including the Wetland Conservation Area and Mai Po and Inner Deep Bay Ramsar Site near the Shenzhen River mouth) will be the same as the baseline concentrations (please refer to the assessment of suspended sediment dispersion in Section 6.7.1).  Disturbed sediments will thus not disperse to the WSRs from the Project Site.  Therefore, the potential of release of total nitrogen, ammoniacal nitrogen and total phosphorus from the disturbed sediments at the WSRs as a result of the construction of the Project is considered negligible. 

It is considered that the potential water quality impacts with respect to increase of heavy metals, nutrients and micro-organic pollutants levels in the receiving water due to release from disturbed/re-suspended sediments are minimal and acceptable.


Table 6.12     Percentage Increase in SS Concentrations under Different Working Conditions during the Construction Phase of the Project

Locations of Construction Works

Working Condition 1

Working Condition 2

Distance from Works Location

Upstream 500 m (b)

Downstream 1,000 m (b)

At Shenzhen River mouth

Upstream 500 m (c)

Downstream 1,000 m (c)

At Shenzhen River mouth

% Increase in Dry Season

Closed Grab

0.0

17.6

0.0

0.0

2.9

0.0

Open Grab

0.0

21.6

0.0

0.0

2.9

0.0

Foundation Pit Drainage

0.0

0.0

0.0

0.0

0.0

0.0

% Increase in Wet Season

 

Closed Grab

0.0

18.9

0.0

0.0

9.8

0.0

Open Grab

0.0

23.0

0.0

0.0

11.8

0.0

Foundation Pit Drainage

0.0

1.4

0.0

0.0

0.0

0.0

Notes:

(a)           According to the WQO of the Deep Bay WCZ, effluent discharge shall not cause a 30% increase in SS level in the natural environment.

(b)           For Working Condition 1, the % change in SS is calculated at an area 500 m upstream of the location of construction activities at Work Area I and an area 1,000 m downstream of the location of construction activities at Work Area II.

(c)            For Working Condition 2, the % change in SS is calculated at an area 500 m upstream of the location of construction activities at Work Area III and an area 1,000 m downstream of the location of construction activities at Work Area IV.


Table 6.13      Results of Elutriate Test Conducted for River Sediment

Sampling Location

Total Nitrogen

(mg L-1)

Total Phosphorus

(mg L-1)

Ammoniacal Nitrogen

(mg L-1)

SR1

5.8

1.6

4.63

SR3

23.2

0.4

18.8

SR5

53.8

1.0

12.5

SR6

12.0

1.5

11.9

SR8

9.0

0.8

6.11

River Water Concentration

7.0

0.6

6.98

Table 6.14      Summary of Assessment Criteria for Dissolved Metals, Organic Compounds and Nutrients

Compound

Unit

Assessment Criteria

Heavy Metals

 

 

Arsenic (As)

ug L-1

340 (a)

Cadmium (Cd)

ug L-1

2 (a)

Chromium (Cr)

ug L-1

16 (a)

Copper (Cu)

mg L-1

1.0 (b)

Lead (Pb)

ug L-1

65 (a)

Nickel (Ni)

ug L-1

470 (a)

Zinc (Zn)

ug L-1

120 (a)

Silver (Ag)

ug L-1

3.2 (a)

PAHs

 

 

Naphthalene

ug L-1

37 (b)

PCBs

 

 

Total PCBs

ug L-1

0.014 (a)(c)

Chlorinated pesticides

 

 

Heptachlor

ug L-1

0.52 (a)

Aldrin

ug L-1

3 (a)

Heptachlor epoxide

ug L-1

0.52 (a)

Alpha - Endosulfan

ug L-1

0.22 (a)

Beta – Endosulfan

ug L-1

0.22 (a)

4,4’ - DDT

ug L-1

1.1 (a)

 

 

 

Nutrients

 

 

Total Nitrogen

mg L-1

2 (d)

Total Phosphorus

mg L-1

0.4 (d)

Ammoniacal Nitrogen

mg L-1

2 (d)

Notes:

(a)        U.S. Environmental Protection Agency (USEPA), National Recommended Water Quality Criteria, 2009 (http://water.epa.gov/scitech/swguidance/waterquality/).  Criterion Maximum Concentration (CMC) values are adopted if not stated otherwise. 

(b)        Australian and New Zealand Environment and Conservation Council (ANXECC), Australian and New Zealand Guidelines for Fresh and Marine Water Quality (2000) – Trigger values for protection of 90% of species.  (http://www.mincos.gov.au/publications/australian_and_new_zealand_guidelines_for_fresh_and_marine_water_quality

(c)        USEPA (2009) Criterion Continuous Concentration (CCC) for freshwater is adopted for total PCBs (e.g., the sum of all congener or all isomer or homolog or Aroclor analyses.)

(d)        Ministry of Environmental Protection of the People’s Republic of China, Environmental Quality Standards for Surface Water (GB 3838 - 2002) – Class V surface Water.

 

Sewage Discharges

Sewage will be generated from the construction workforce, site office’s sanitary facilities and from portable toilets.  If not properly managed, these wastewaters could cause adverse water quality impacts, odour and potential health risks to the workforce by attracting pests and other disease vectors.

It is estimated that up to 1,350 construction workers will be involved in the construction of the Project during the peak construction period.  With a sewage generation rate of 0.15 m3/worker/day ([7]), about 203 m3 of sewage will be generated per day.  It is estimated that about 45 portable toilets will be required ([8]).  However, the exact number of portable toilet required will be based on the contractor practice, as well as the site condition.  Nevertheless, an adequate number of portable toilets will be provided at the Project Site to ensure that sewage from site staff is properly collected.  No adverse environmental impacts are envisaged provided that the portable toilets are properly maintained by a contractor and the collected sewage is disposed at the designated sewage treatment works. 

Land Based Construction Activities (including the advanced works)

Discharges and runoff from the Project Site during the construction phase, particularly during soil excavation, filling of embankment foundation, slope protection, and landscaping works, will contain SS which could be a source of water pollution.  Wastewater with high pH value may be generated by concrete washing during slope protection works and in situ concreting works.  However, with proper implementation of general good construction site practices as described in Section 6.8, it is anticipated that the land based construction works will not cause adverse water quality impact.

6.7.2                                Operation Phase

Hydrodynamic Assessment

River improvement works will be carried out under the Project in order to rectify the flood prevention performance of the regulated section of Shenzhen River (ie to attain the drainage capacity of a 50-year return period) and to safeguard the livelihood of settlements along the river. 

In relation to the above, changes in hydrodynamic conditions after implementation of the Project, especially the changes in water surface profile of the river before and after the implementation of the Project, have been assessed by mathematical model.

In the hydraulic model calculations, the hydraulic elements of Shenzhen River under different design conditions (ie before and during the implementation of the Project and one year after operation) have been simulated.  The flood control standard before implementation of the Project is 1 in 2 to 20 years, and after implementation of the Project, it will achieve the 1 in 50 year standard.  The working conditions for the modelling were formulated as follows:

·           Condition 1: Before and after the implementation of the Project, the flood surface profile when 1 in 50 years flood encounters 1 in 50 years tidal level;

·           Condition 2: Before and after the implementation of the Project, the flood surface profile when 1 in 50 years flood encounters 1 in 10 years tidal level;

·           Condition 3: Before and after the implementation of the Project, the flood surface profile when 1 in 10 years flood encounters 1 in 50 years tidal level;

·           Condition 4: Before and after the implementation of the Project, the flood surface profile when 1 in 10 years flood encounters 1 in 10 years tidal level;

·           Condition 5: One year after the implementation of the Project, the flood surface profile when 1 in 50 years flood encounters 1 in 50 years tidal level;

·           Condition 6: One year after the implementation of the Project, the flood surface profile when 1 in 50 years flood encounters 1 in 10 years tidal level;

·           Condition 7: One year after the implementation of the project, the flood surface profile when 1 in 10 years flood encounters 1 in 50 years tidal level; and

·           Condition 8: One year after the implementation of the project, the flood surface profile when 1 in 10 years flood encounters 1 in 10 years tidal level.

Detailed modelling methodology is discussed in Annex C1.

Modelling results showing water surface profiles before (ie before construction) and after implementation (ie during operation) of the Project under different flood and tidal conditions (ie working conditions 1 to 4) are illustrated in Figures C-5 to C-8 of Annex C2.  By achieving the flood control standard of 1 in 50 years after implementation of the Project, water level of the regulated river section of the Project will be lower than the water level before implementation under all the four working conditions of tidal and flood levels (working conditions 1 to 4).  It is thus considered that implementation of the Project will be beneficial to the hydrodynamics of the Project Site by improving the flood prevention performance.  However, due to tidal influence from Deep Bay, water level during operation phase at river section downstream of Ping Yuen River confluence (ie downstream of the Project Site) will be similar to the original water level before implementation of the Project under all working conditions.  Therefore, implementation of the Project is not expected to significantly affect the hydrodynamic conditions downstream of the Project Site, and hence Wetland Conservation Area and Mai Po and Inner Deep Bay Ramsar Site near the Shenzhen River mouth. 

After one year of implementation, water level within the Project Site under the four combinations of flood and tidal frequency (ie working conditions 5 to 8) will be lower than the designed water level due to channel erosion (see Figure C-9 to C-12 of Annex C2).  Water level after one year of implementation will be lower than the designed level by a maximum of 1 m.  However, due to deposition of river sediments between Ping Yuen River confluence and Ng Tung Rive confluence, water level after one year of operation will be higher than that of the designed water level as indicated by the modelling results under all the four combinations of flood and tidal frequency for working conditions 5 to 8.  Detailed discussions on the channel erosion and sediment deposition along the Shenzhen River are provided below.

Erosion and Sediment Deposition of Riverbed

The variations of channel erosion and sediment deposition after the implementation (ie during operation) of the Project have been assessed.  The working conditions for the modelling were formulated as follows:

-          Condition 1: Before implementation of the Project, erosion and deposition of riverbed experiencing one year’s flow and sediment;

-          Condition 2: After implementation of the Project, erosion and deposition of riverbed experiencing one year’s flow and sediment;

-          Condition 3: After implementation of the Project, erosion and deposition of riverbed experiencing two consecutive typical water and sediment years;

-          Condition 4: After implementation of the Project, erosion and deposition of riverbed experiencing three consecutive typical water and sediment years.

Detailed modelling methodology is presented in Annex C1 and results of the four working conditions are illustrated in Figures C-13 to C-14of Annex C2.

Modelling results presented in Table 6.17 indicate that net erosion of river bed is expected to occur within the Project Site before and after one, two and three years of operation of the Project as a result of steeper gradient in this river section compared with the downstream section (see Figure C-13 of Annex C2).  Negative values for deposition thickness and volume are predicted in this river section (see Table 6.15).  The section between Ping Yuen River confluence and Ng Tung River confluence is the main receiving body of upstream sediments and hence net deposition of sediments is expected to occur under all the four working conditions reflecting by the positive deposition thickness and volume (see Table 6.15).  The maximum sediment deposition is anticipated between Ng Tung River confluence and Huanggong River confluence due to sediments flowing from upstream section and Buji River and tidal influence from Deep Bay.  Maximum sediment deposit thickness of 0.43 m and volume of approximately 100,000 m3 are predicted by the model after one year of Project implementation (ie working condition 2), which is similar to those before construction of the Project (ie working condition 1).  Incoming tide from Deep Bay is the source of deposited sediments between Huanggong River confluence and Shenzhen River mouth, therefore, unacceptable impacts at the Wetland Conservation Area and Mai Po Reserve as a result of sediment deposition caused by the Project implementation is not expected. 

From the modelling results, a general trend of decreasing deposition volume and thickness with time after implementation of the Project at river section downstream of Ping Yuen River confluence is observed (ie working conditions 2 to 4 on Table 6.15) as the deposition soon reaches equalibrium.  However, maintenance dredging, say 3 to 5 years, would still be required downstream of the Project Site to remove the deposited sediment in order to maintain the overall flood prevention performance of the Shenzhen River.

Water Quality

Levels of key water quality parameters (DO, COD, BOD5, total nitrogen, total phosphorus and ammoniacal nitrogen) along Shenzhen River were modelled under working conditions of with (during operation) or without the Project (baseline) for both wet and dry seasons.  The water quality impacts were assessed by comparing the differences in water quality parameters between the baseline and operation conditions.  Figures illustrating the modelling results are included in Annex C2.  The modelling results show that levels of COD, BOD5, total nitrogen, total phosphorus and ammoniacal nitrogen during the operation phase would be equal to or less than those of the baseline situation in both wet and dry seasons (see Figures C-17 to C-26 of Annex C2).  For DO, the values during operation are equal to or higher than those of the baseline in both seasons (see Figures C-15 and C-16 of Annex C2).  It should be noted that the model calculations have taken account of the effects of sewage collection and diversion works on the Shenzhen side of the river.  Overall, no unacceptable water quality impacts are expected from operation of the Project.


Table 6.15     Thickness of Volume of Sediment Deposition on the River Bed under different Working Conditions

River Section

Most upstream point of Stage 4 to Ping Yuen River Confluence

Ping Yuen River Confluence

to Ng Tung River Confluence

Ng Tung River Confluence

to Huanggong River Confluence

Huanggong River Confluence

to Shenzhen River Mouth

 

Deposition thickness (m)

Deposition volume (m3)

Deposition thickness (m)

Deposition volume (m3)

Deposition thickness (m)

Deposition volume (m3)

Deposition thickness (m)

Deposition volume (m3)

Working Condition 1 -

After 1 year under existing conditions

 

-1.14

-45,201.66

0.41

101,793.10

0.44

397,181.10

0.10

42,236.15

Working Condition 2 -

After 1 year of Operation

 

-0.29

-22,498.37

0.39

93,952.20

0.43

409,950.04

0.12

46,980.42

Working Condition 3 –

After 2 years of Operation

 

-0.17

-11,735.01

0.07

16,421.00

0.09

79,352.16

0.11

39,164.06

Working Condition 4 –

After 3 years of Operation

-0.08

-3,196.52

0.07

16,078.40

0.08

69,436.13

0.11

39,703.51

Note:

(a)        Existing conditions refer to the river bed before the construction of the Project.

 


Maintenance Dredging

Within the Project Site where the river course is straightened and widened, a trend of continuous sediment erosion is anticipated due to greater difference in elevation of this river section.  Modelling results of sediment transport during the operation phase presented above indicate that a total of approximately 22,500 m3 and 11,700 m3 of sediments will be eroded from the Project Site and deposited on the river section downstream of the Ping Yuen River confluence after one and two years of Project implementation, respectively.  As such, it is anticipated that the need for maintenance dredging within the Project Site is minimal.  However, in case where maintenance dredging is needed, it is anticipated that it will be undertaken infrequently and in small and localised scale during dry season (October to March), with a dredging rate less than that during the construction phase, ie 996 m3 day-1.  The impact of maintenance dredging to SS concentrations is thus expected to be insignificant.

Sedimentation at the flood retardation pond is anticipated.  Given the nature of the flood retardation pond, river water will only be required to enter the pond during wet season after severe rainstorm events.  Hence, the frequency for maintenance dredging required at the pond will be low.  Since the flood retardation pond is a confined area, the suspended river sediments associated with maintenance dredging will eventually settle within the pond without causing any SS elevations in the river.  Unacceptable river water quality impacts are thus not anticipated.

The modelling results indicate that after one year operation of the Project, the increase in sediment deposition in the river sections from Ng Tung River Confluence to Huanggong River Confluence and from Huanggong River Confluence to Shenzhen River Mouth is 12,770 m3 and 4,700 m3, respectively (please refer to Working Condition 2 of Table 6.15).  Part of the increase is due to tidal effect.  After the second and third year of operation, the amount of deposited sediment in the two river sections will become less than that of the baseline condition.  It is thus considered that the insignificant increase in sediment deposition will not increase the scale of the routine maintenance dredging downstream of the Project Site.  No additional water quality impacts as a result of the implementation of the Project is expected to occur.

Overall, unacceptable impacts to SS concentrations caused by maintenance dredging are not expected to occur. 

6.8                                      Mitigation Measures

6.8.1                                Construction Phase

Cofferdam Demolition

The impacts to water quality from the loss of sediment to suspension were assessed during the cofferdam demolition which involves wet excavation.  The assessment was based on the predicted loss rates of fine sediments to suspension from open grab and closed grab working at different locations during the times of peak excavation rate.  The highest loss rate was predicted to occur during the time at which the maximum rate of wet excavation was occurring.  The maximum loss rate was then adopted in the Study and it was predicted that this loss rate would not give rise to adverse water quality impacts.  Nevertheless, good practices is recommended to further minimise the water quality impact.  It is therefore recommended that the maximum loss rate during the wet excavation should be kept at or below these limits. 

The following good practices shall apply at all times:

·           Dry excavation will be used, as far as practicable, for cofferdam excavation.

·           Attention will be paid to the lifting speed of the grab to minimise the loss of sediment.

·           Excavated sediment will be disposed of in a gazetted marine disposal area in accordance with the Dumping at Sea Ordinance (DASO) permit conditions (as discussed in the Land Contamination and Waste Management Assessment Report).

·           The marine vessels ([9]) for transport of sediment to the marine dumping ground will be fitted with tight bottom seals in order to prevent leakage of material during transport.  The barges will be filled to a level, which ensures that material does not spill over during transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action.

·           The contractor(s) will confirm that the works cause no visible foam, oil, grease, litter or other objectionable matter to be present in the water within and adjacent to the excavation site.

·           For concurrent excavation works at adjacent work areas (ie Work Areas I and II, and Work Areas III and IV), construction will be carried out along the same flow direction (ie from upstream to downstream / downstream to upstream) to minimise the overall impacts to SS concentrations from adjacent work areas.

With the proper implementation of the recommended mitigation measures during cofferdam demolition works, no unacceptable water quality impacts will occur.

Construction Site Runoff and Drainage

Good construction site practices outlined in ProPECC PN 1/94 Construction Site Drainage” will be followed as far as practicable in order to minimise surface runoff and the chance of erosion, and also to retain and reduce any suspended solids in surface runoff prior to discharge.  These practices include the following:

·           Silt removal facilities such as silt traps or sedimentation facilities will be provided to remove silt particles from runoff to meet the discharge standards of the TM-ICW under the WPCO.  The design of silt removal facilities will be based on the guidelines provided in ProPECC PN 1/94.  All drainage facilities and erosion and sediment control structures will be inspected on a regular basis and maintained to confirm proper and efficient operation at all times and particularly during rainstorms.  Deposited silt and grit will be removed regularly.

·           Excavation within cofferdam will be maintained in dry condition as far as possible.  Water within the cofferdam will be discharged to the river before excavation commences and at times when needed (eg after heavy rain).  Adequate time (48 hours) will be allowed for suspended solid to settle (potentially overnight) before foundation pit drainage are being discharged outside the works area.

·           Non-active area along the river bank will be covered by impermeable sheets or hydroseeding completed sections immediately whenever possible to minimise erosion of soil by runoff particularly during heavy rainstorms.

·           Earthworks to form the final surfaces will be followed up with surface protection and drainage works to prevent erosion caused by rainstorms.

·           Appropriate surface drainage will be designed and provided, where necessary.  In particular, surface runoff will be collected along the river bank and be diverted to sedimentation tank/pond before discharge into the river

·           The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.

·           Oil interceptors will be provided in the drainage system where necessary and regularly emptied to prevent the release of oil and grease into the stormwater drainage system after accidental spillages.

·           Temporary and permanent drainage pipes and culverts provided to facilitate runoff discharge will be adequately designed for the controlled release of storm flows.

The temporary diverted drainage will be reinstated to the original condition when the construction work has finished or when the temporary diversion is no longer required. 

The dredged sediment will be temporary stored in the stockpile areas for dewatering by natural ventilation.  Runoff from these stockpile areas will be collected for treatment by sedimentation with the addition of coagulant.  The treated water will be reuse on site for water spraying.

Sewage Discharge

An adequate number of portable toilets will be provided for the on-site construction workforce ([10]).  Wastewater/sewage will be transferred to the Luofang Sewage Treatment Works in Shenzhen (during the river modification and associated works) or a Government sewage treatment works in HKSAR (during the advanced works) by a reputable collector.

General Construction Activities

·           Debris and refuse generated on-site will be collected, handled and disposed of properly to avoid entering the nearby WSRs.  Stockpiles of cement and other construction materials will be kept covered when not being used.

·           Oil leakage or spillage will be contained and clean up immediately.  Waste oil will be collected and stored for recycling or disposal in accordance with the Waste Disposal Ordinance.

6.8.2                                Operation Phase

Hydrodynamics

The hydrodynamic modelling has predicted that the operation of the Project will be beneficial to the Project Site by improving its flood prevention performance and no adverse impacts to hydrodynamics are expected to occur at the sensitive receivers.  Mitigation measures are thus not considered to be necessary.

Channel Erosion and Deposition

Eroded sediment flowing from the Project Site will be deposited between Ping Yuen River confluence and Huanggong River confluence and consequently affecting the flood prevention performance of this section.  Maintenance dredging, which would mainly be undertaken outside the Project Site, would be required to rectify the flood prevention performance.

Water Quality

Sewage from the Shenzhen side currently discharged to the Project Site will be collected and diverted to the sewage treatment works, which will effectively reduce the pollutants discharge to the river.  The water quality of the Shenzhen River during the operation of the Project will be improved and mitigation measures are thus not considered to be necessary. 

Maintenance Dredging

No adverse water quality impact due to maintenance dredging is predicted. Mitigation measures are not considered to be necessary.

6.9                                      Residual Impacts

With the proper implementation of the recommended mitigation measures, no residual environmental impacts are envisaged from the construction and operation of the Project.

6.10                                  Cumulative Impacts

According to publicly available information, the following major developments in north eastern part of Hong Kong will be constructed and/or operated concurrently with the construction and operation (ie maintenance dredging) of the Project.

·           Liantang/Heung Yuen Wai Boundary Control Point (LT/HYW BCP) and the associated road works;

·           Construction of a Secondary Boundary Fence (SBF) and New Sections of Primary Boundary Fence (PBF) and Boundary Patrol Road (BPR) ([11]); and

·           Drainage Improvement in Northern New Territories – Package C (Remaining Works) ([12]).

There are also two ongoing planning studies with study areas within and in the vicinity of the Project Site:

·           Land Use Planning for the Closed Area; and

·           New Development Areas in North East New Territories (NENT NDAs).

The construction of the LT/HYW BCP and the connecting roads is scheduled to commence in mid 2013 and be completed in mid 2018 ([13]).  With implementation of proper mitigation measures, unacceptable water quality impacts would not be expected to occur during construction of the BCP.  During the operation phase, additional surface runoff from the BCP will be discharged into the Shenzhen River which constitutes approximately 2.2 % of the existing peak flow of the Shenzhen River near the Ping Yuen River confluence.  Before discharge into the Shenzhen River, stormwater and surface runoff from the BCP will be collected by a drainage system and treated using standard silt trap (or grease trap if necessary) and oil interceptor at the Public Transport Interchange and vehicles holding area to remove the oil, lubricants, grease, silt and grit.  Hence, no adverse water quality impacts are anticipated to be caused by the discharge.  Sewage and wastewater effluents generated from the staff, food and beverage outlets and passengers of the BCP will be directed to a high level wastewater treatment plant using Membrane Bioreactor treatment (MBR) technology, which will be designed with a treatment capacity of 387.56 m3 d-1.  About 178.75 m3 d-1 of the treated effluent will be reused on site for irrigation and flushing and the remaining effluent will be discharge to the Deep Bay via gravity sewers in order to meet the requirement of no net increase in pollutants loading of the receiving water body.  As the discharge will have no net increase in pollutants loading, unacceptable cumulative water quality impacts are not expected to occur during the operation phase.

The construction of the SBF and new sections of PBF and BPR only involves land-based construction works.  According to the latest tentative programme, the works from Ng Tung River to Ping Yuen River will be carried out between end 2011 and early 2013, while the works from Pak Fu Shan to Lin Ma Hang Road will be carried out between end 2011 and end 2013.  With proper implementation of the recommended mitigation measures in the EIA study, no residual impacts are anticipated from the construction and operation of this project ([14]).  Moreover, the reprovisioning of a section of the border patrol road and boundary fences within the Project area will be incorporated into the design and construction programme of this Project (as advanced works).  The potential water quality impacts associated with the reprovisioning of the SBF and the associated patrol roads have been assessed in this EIA.  

The construction activities for the drainage improvement works of Package C is scheduled to commence in July 2012 and be completed in December 2014 (ie overlapped with the construction phase of Stage IV regulation) ([15]).  However, details regarding its water quality impact assessment are not yet available and thus assessment of the cumulative water quality impacts is not possible at this stage.

The development schedule and programme of the Closed Area Study and the NENT NDAs Study are not available at this stage.  However, it is anticipated that the construction of the new developments planned under these studies will not be carried out concurrently with the construction of this Project.  

No unacceptable cumulative water quality impacts are expected.

6.11                                  Environmental Monitoring and Audit

6.11.1                            Construction Phase

With proper implementation of the recommended mitigation measures, sediment dispersion is not expected to cause adverse water quality impacts at the identified water sensitive receivers.  However, a monitoring programme is recommended to verify the predictions of the EIA and ensure compliance with the assessment criteria.

Water quality monitoring will be undertaken during the foundation pit drainage and cofferdam demolition at the following locations:

During foundation pit drainage and cofferdam demolition at Work Area I and Work Area II

·           500 m upstream of Work Area I; and

·           1,000 m downstream of Work Area II.

During foundation pit drainage and cofferdam demolition at Work Area III and Work Area IV

·           500 m upstream of Work Area III; and

·           1,000 m downstream of Work Area IV.

There will be one monitoring station at each location (ie a total of four monitoring stations).  Monitoring will be conducted for three times per week during the construction period.  The interval between two sampling surveys will not be less than 36 hours.  During each sampling survey, water samples for laboratory analysis and in situ measurements will be taken at all monitoring stations for the following water quality parameters:

·           Dissolved Oxygen (mg L-1) (in situ);

·           pH (in situ);

·           Turbidity (NTU) (in situ); and

·           Suspended Solids (mg L-1) (laboratory analysis).

Monthly site inspections and audits will be conducted to ensure that the recommended mitigation measures are properly implemented during the construction stage.

6.11.2                            Operation Phase

Adverse water quality impact is not expected during operation phase and hence monitoring is not considered necessary.  In fact the water quality will be monitored through the existing monitoring programme along Shenzhen River

6.12                                  Conclusion

The potential sources of water quality impacts associated with the construction and operation of the Project have been identified and the potential impacts were evaluated using proven mathematical models.  The modelling has assessed a number of scenarios (including a number of worse case scenarios) for pollutants (including SS, heavy metal, nutrients and micro-organic pollutants) releases from the construction activities, and maintenance dredging and the change of the hydrodynamic conditions of the river during the operation of the Project.   

Potential impacts arising from the proposed construction works are predicted to be largely confined to the specific works areas.  With proper implementation of the recommended mitigation measures, sediment dispersion is not expected to cause adverse water quality impacts at the identified WSRs. 

During the operation phase, changes to hydrodynamic regime within the Project Site are predicted to be beneficial and no adverse impacts are anticipated.  Adverse water quality impacts are not expected at any identified WSRs due to the operation of the Project.  It is envisaged from the modelling results of sediment erosion and deposition that maintenance dredging would be required between the Ping Yuen River confluence and Huanggong confluence to maintain the flood prevention performance of this section of the Shenzhen River.  Within the Project Site, the scale and volume of the maintenance dredging activity will be significantly smaller than that of the capital construction work.  Adverse water quality impact is not expected.

With the implementation of the recommendation mitigation measures, no residual water quality impacts are envisaged due to the construction and operation of the Project.  Nevertheless, a monitoring programme is recommended during construction phase to verify the predictions of the EIA and ensure compliance with the assessment criteria.

Cumulative water quality impacts associated with concurrent projects within the Study Area have been considered, no adverse impact is anticipated.


 



([1])   EPD (2006) Annual River Water Quality Report..  http://www.epd.gov.hk/epd/english/environmentinhk/water/river_quality/rwq_report.html

([2])   EPD (2007) Annual River Water Quality Report..  http://www.epd.gov.hk/epd/english/environmentinhk/water/river_quality/rwq_report.html

([3])   EPD (2008) Annual River Water Quality Report..  http://www.epd.gov.hk/epd/english/environmentinhk/water/river_quality/rwq_report.html

([4])   EPD (2008) Op. cit.

([5])     深圳市水務規劃設計院及博威工程顧問有限公司 (2010) 深圳河上游與蓮塘/香園圍口岸相關河段治理工程規劃及可行性研究

([6])        DSD (2000)  Shenzhen River Regulation Project Stage III. - EIA Report.  Register no. AEIAR-035/2000.

([7])   Table 2 of the Drainage Services Department's Sewerage Manual. 

([8])   Based on experience in construction sites in Hong Kong, one portable toilet can serve about 30 workers.

([9])     It should be noted that the sediments will be transported off-site by trucks to the berthing area at Shenzhen and then loaded to a barge for bulk transfer to the marine dumping ground.  This measure is referred to the control of the barge.

([10]) It is estimated that about 45 portable toilets will be required based on the assumptions that one portable toilet can serve 30 workers.

([11])     The advance works of this Project is part of the Secondary Boundary Fence project, which was entrusted to DSD.

([12])     DSD (2010) Drainage Improvement in Northern New Territories – Package C (Remaining Works) – Project Profile (Application No. ESB-216/2020).

([13])      CEDD (2008) Liantang / Heung Yune Wai Boundary Control Point and Associated Works - Project Profile (Application No. ESB-199/2008).

([14])      Mott MacDonald (2009) Construction of a Secondary Boundary Fence and New Sections of Primary Boundary Fence and Boundary Patrol Road - EIA Report. (Register No. AEIAR-136/2009).

([15])     DSD (2010) Op. cit.